1. Project background: a meter with a special protocol blocks data acquisition

Project overview

• Location: Gangxi PV Plant, Chongqing (CGN Chongqing)

• Scope: energy monitoring for a grid-connected PV generation project

Core challenge: how to acquire data efficiently from EDMI meters

DLMS & EDMI Meter Data Acquisition (Gangxi PV Plant, Chongqing)

When an EDMI protocol meter (Mk6E) has to be monitored in real time, how do you do it without dismantling the meter or modifying any wiring?

Implementation constraints

• Meter restrictions: on-site meters may not be opened or rewired

• Interface restrictions: only the optical (infrared) communication port is available

• Unusual protocol: not a standard State Grid protocol, which makes parsing difficult

• Clear requirements: low cost, minimal wiring, wireless transmission

2. Technical approach: reading through the infrared port to get past the protocol barrier

DLMS & EDMI Meter Data Acquisition (Gangxi PV Plant, Chongqing)

Core technical path

An infrared reading + 4G wireless transmission solution matches the characteristics of the optical communication port on the EDMI Mk6E meter, with no need to open the meter or change any wiring.

Solution components

• Hardware: SC-GP-IR4G 4G infrared meter reading device

• Software: general-purpose data acquisition software (DAQ FOR IIOT)

• Key accessory: near-infrared data acquisition probe

DLMS & EDMI Meter Data Acquisition (Gangxi PV Plant, Chongqing)

Technical advantages

• Protocol support: the difficulty of reading and parsing the EDMI protocol has been fully resolved

• Easy installation: no meter dismantling — only the optical communication port is used

• Remote management: remote commissioning and configuration

• Data integration: MQTT + JSON standard format, compatible with the customer’s platform

3. On-site implementation: how the deployment was completed quickly

DLMS & EDMI Meter Data Acquisition (Gangxi PV Plant, Chongqing)

DLMS & EDMI Meter Data Acquisition (Gangxi PV Plant, Chongqing)

Implementation steps

  1. Mount the infrared probe.

2. Power the acquisition device on site

3. Commission and configure remotely

4. Integrate the data with the customer’s platform

Data transmission standard

• Protocol: MQTT

• Format: JSON with custom fields

• Bearer: 4G wireless network

4. Results: what data is now being acquired

Key data points

• Total forward active energy

• Forward active energy by peak / flat / valley tariff period

• Total reverse active energy and energy by period

• Total forward reactive energy and energy by period

DLMS & EDMI Meter Data Acquisition (Gangxi PV Plant, Chongqing)

Project value

✅ Infrared reading of EDMI protocol meters achieved

✅ No meter dismantling or rewiring — on-site modification kept to a minimum

✅ 4G wireless transmission, low cost and easy to deploy

✅ Real-time data monitoring that keeps the PV plant running efficiently

5. Service support: who to call for hard-to-read meters

Shanghai Daq IoT

A specialist provider of IoT data acquisition solutions, focused on meters with unusual protocols and on industrial equipment data acquisition.

Contact us

• Enquiries

• Website:

• Our promise: make data acquisition simpler.